The Fields Update March 2019

Title for STAGE ONE The Fields was issued this morning (Note Developer for The Fields is Richmond West Development Company Ltd). The barriers in front of Berryfield bridge will now soon be removed.

STAGE TWO: By working to the guidelines of “Section 91: Exemption Process for Spark and Heat Hazardous Activities” Ching Contracting have been able to continue progressing well with construction. All underground services (stormwater, water & sewer) are now installed and work will start on kerbing later this week. PS this is a pre Christmas drone photo as there is no green grass down there now!!